Gatwick - Temporary Roof Scaffolding

The scaffold was a temporary roof with 2 Multi Directional Lifting Gantries suspended from the roof. It was erected on the South Terminal F.C.C. Project in June/July 2024. We have also provided 2 x 750kg hoists for lifting from the gantries.

This was built Airside and in a tricky location meaning that logistically getting the material to site involved a lot of work. TONE Scaffolding also had to crane up roof trusses which were assembled in our yard, transported by trailer to the airport and lifted up in in 13m sections. This was carried out at night in very short working windows due to restrictions on crane use at the airport.